Vermeersdairy

Photo Gallery 4

August 5th

Today  for the very first time the  rotary did one full rotation, this is the very first time!

Workers are prepping the crowd gate/holding area for cementing

Text Box:

In this picture you can vaguely see part of the ceiling on the right this was put in today also you can see the row of stalls

The photographer is standing in the alley between the livestock barn and the rotary barn this is the east side of the barn your looking at.

The photographer is standing on the west side of the barn, your looking at the east side.

This website was made and designed by ;

 

 

 

Jake Vermeer
Text Box: August 11th

This is half of the holding area has yet to be cemented

In this picture you can vaguely see the other half of the holding area cemented

The floor is ready to be poured

A view of the total barn

Western view of the barn

The ceiling is almost in the whole barn

Text Box: August  27th

Some of the head gates in the livestock barn are in

The concrete for the feed alley is being prepared and by this time should already be poured every where

The rotary is nearing completion and the structure supports are in place

The holding area is already cemented and the crowd gate is being installed and some gates are hanging up

The due date for the barn is September 5th, cows will be moved the morning of September the 5th

Text Box: October 7th

Were putting feed into the empty barn, which is awaiting cows

The trucks have arrived. Three trucks travelled twice between the two farms

Cows are coming off the trucks

The cows are in the barn

The first time the rotary is full of cows